Risk manager Maria Sanchez is evaluating her employer’s current fleet of vehicles to ensure they are roadworthy and determine if any replacements are needed. Maria’s activities are part of which one of the following steps in the risk management process?

Insurance

Are you looking for the correct answer to the question “Risk manager Maria Sanchez is evaluating her employer’s current fleet of vehicles to ensure they are roadworthy and determine if any replacements are needed. Maria’s activities are part of which one of the following steps in the risk management process?”? If that’s the case, you don’t have to worry anymore. AzAnswer team is here with the right answer to your question. Please check below to know the answer.

Risk manager Maria Sanchez is evaluating her employer’s current fleet of vehicles to ensure they are roadworthy and determine if any replacements are needed. Maria’s activities are part of which one of the following steps in the risk management process?

Options

A. Analyzing loss exposures

B. Monitoring results and revising the risk management program

C. Identifying loss exposures

D. Implementing the selected risk management techniques

Answer: B

The above question Risk manager Maria Sanchez is evaluating her employer’s current fleet of vehicles to ensure they are roadworthy and determine if any replacements are needed. Maria’s activities are part of which one of the following steps in the risk management process?, Was part of Insurance MCQs & Answers. I hope you got the correct answer to your question. Have a great time ahead.